Shut Down the Entire Cluster
To perform an orderly shutdown of the entire cluster:
1. Log on to the D-SRV, and start Cluster Administrator.
2. For each role in the cluster (LC1, LC2, LC3, and DS1), select the role, right-click,
and select Take Offline.
3. Power off the A-SRV.
4. Power off all CAs.
5. Power off the D-SRV.
Start Up the Entire Cluster
To perform an orderly start up of the entire cluster:
1. Power up the D-SRV.
2. Power up the A-SRV.
3. Power up the CAs.
4. Wait for five minutes.
5. Log on to the D-SRV, and use Cluster Administrator to bring the DS1 role on line,
as follows:
a. Right-click the DS1 group.
b. Select Bring Online.
6. Use the Cluster Administrator to bring the LC Roles online one at a time. Wait for
each role to come online before starting the next role.
As you bring each LC Role online, make sure that the LC Role is assigned to a
unique CA. If each LC Role is not assigned to a unique CA, reassign it as follows:
a. Right-click the LC Role.
b. Select Move Group.
c. Select a CA that is not assigned a role.
Related Articles
How to shut down RSA Mobile from the command line 6Number of Views How To Shut Down The Envision Nodes In A Distributed Site 28Number of Views How to determine time necessary to complete an sdconnect shutdown in RSA ACE/Server 32Number of Views Edit, Restart CM, Reboot Appliance and Shutdown Appliance buttons under the Admin > System > Appliance tab are deprecated … 89Number of Views Authentication Manager database services do not to start after power outage 189Number of Views
Trending Articles
RSA Authentication Manager 8.9 Patches and Hotfixes Readme RSA Authentication Manager 8.9 Setup and Configuration Guide AFX Server and Remote Collection Agents fail to start after updating Java to version 1.8u241 (1.8.0_241) / 1.7u251 (1.7.0_… Upgrade Internal Authentication Manager Certificates to SHA-256 Authentication Manager Supported Hardware and Upgrade Paths